It is possible to move all the cycle setpoints from an old control board to a new control board. The procedure is as follows:
- Remove the U2 chip from the old control board. The U2 chip is located on the small board (SBC196) on the main control board. The U2 chip is an 8-pin chip
- Turn off the power on the new board
- Remove the U2 chip and set it aside
- Install the U2 chip from the old board on the new board
NOTE
MAKE SURE TO ENSURE THE NOTCH IN THE CHIP MATCHES THE NOTCH ON THE BOARD
- Switch the OP CAL switch to OP
- Turn on the sterilizer and check the setpoints
- Turn the power off and place the OP CAL switch in the CAL position
- Turn the power on and calibrate the RTDs and pressure
- Turn the power off and move the OP CAL switch to OP
- Turn the sterilizer on and run test cycles
Have a question or having difficulties? Talk to Dave Schall, our PRIMUS sterilizer expert who is here to assist you anytime at 877.679.7800 extension 1212 or email at dschall@spire-is.com.