It is possible to move all the cycle setpoints from an old control board to a new control board. The procedure is as follows:

  • Remove the U2 chip from the old control board. The U2 chip is located on the small board (SBC196) on the main control board. The U2 chip is an 8-pin chip
  • Turn off the power on the new board
  • Remove the U2 chip and set it aside
  • Install the U2 chip from the old board on the new board

NOTE
MAKE SURE TO ENSURE THE NOTCH IN THE CHIP MATCHES THE NOTCH ON THE BOARD

  • Switch the OP CAL switch to OP
  • Turn on the sterilizer and check the setpoints
  • Turn the power off and place the OP CAL switch in the CAL position
  • Turn the power on and calibrate the RTDs and pressure
  • Turn the power off and move the OP CAL switch to OP
  • Turn the sterilizer on and run test cycles


Have a question or having difficulties? Talk to Dave Schall, our PRIMUS sterilizer expert who is here to assist you anytime at 877.679.7800 extension 1212 or email at dschall@spire-is.com.